Monday, July 26, 2021

Sherwin-Williams' 2nd HQ tower may rise sooner, not later

Outlined in red at the center of this model is Sherwin-Williams'
proposed second headquarters office tower, located to the left
of its larger first-phase. The second tower is shown here as a
largely featureless massing as it lacks a pending construc-
tion start date. But there are indications that the coatings
giant may have some end-users for the tower and a de-
sire to build the tower sooner rather than later (TV20).
CLICK IMAGES TO ENLARGE THEM

In models and on graphics, it was presented almost as an afterthought. It was a featureless box standing in downtown Cleveland at the northeast corner of West Superior Avenue and West 6th Street. Next door, the 600-footer served as a magician's tool of misdirection, with its primary role as the global headquarters of Sherwin-Williams (SHW).

But that blank box, a future HQ tower standing what appears to be about 300 feet tall based on the height of the Rockefeller Building across the street, could not be ignored by a joint meeting of city planning review committees on July 20.

To put the size of that building into context, the Ernst & Young Tower (E&Y) built in 2013 at 950 Main St. as part of the Flats East Bank development stands 23 stories and 330 feet tall. It is one of downtown's few trophy-class buildings -- the only office class above Class A. E&Y has the third-highest rents downtown and is 97 percent full, according to real estate brokerage Jones Lang LaSalle.

SHW's proposed second office tower was labeled on site plans as "Future Sherwin-Williams Expansion TBD" -- To Be Determined. Committee members wanted to determine what it would be and how soon will SHW build it. The reason is that an ugly, unwanted surface parking was shown as temporarily occupying that spot until the expansion building could be built.

The phase two office tower is located at the lower-left portion
of this SHW HQ master plan. It also has for its future phases
sections of lower-level mixed-uses along West 6th Street and
St. Clair Avenue to be developed by others (SHW).

"I've been on this (city planning) committee for a long time," responded a skeptical Thomas Zarfoss, a retired landscape architect. "Whenever I hear the term 'temporary' it gets my attention."

How long would that parking lot remain as "temporary"?

Timothy Muckley, SHW's director of corporate real estate, declined to give a date of when that future expansion would be built. And that future expansion also includes the east and south flanks of West 6th and St. Clair Avenue, labeled on conceptual planning documents as "Future Commercial Retail & Office TBD" and standing several stories tall.

"We've made this mistake with manufacturing plants of not planning for the future," Muckley said. "We want this to be our headquarters site for a long time. It's important to be able to have that for growth."

For logistical reasons, the second tower may be difficult to build at the same time as the 616-footer. HQ design team sources said SHW construction firms need the space for materials staging for the main tower, parking deck and Public Square pavilion. A smaller construction staging area, such as north of Frankfort, might suffice for the second tower which Muckley said would have no additional parking of its own.

Here's where it gets interesting...

This model of the SHW HQ shows a slightly shorter phase two
office tower, standing between a massing of the first phase to
the left and the Rockefeller Building to the right (TV20).

Muckley told the planning committee members that SHW is encouraging companies with whom it does business about locating new sales/administrative offices or relocated corporate offices in those future expansion spaces.

"We work with a lot businesses and we'll urge them to locate next door," Muckley said.

For months, NEOtrans was hearing rumors that SHW was actively seeking leases in its HQ tower by other office tenants. The rumor didn't make sense at the time. Why would a company seeking to build a 1-million-square-foot HQ -- with all of the HQ space already spoken for by most Cleveland SHW offices including an 8 percent growth factor -- make that HQ tower available to other tenants?

Because SHW isn't making the main HQ tower available to other tenants. It's making the second HQ tower available to other tenants. An employee of one of those tenants, based on the East Coast, reached out to NEOtrans months ago saying their company would open an office in Cleveland once SHW opened its new HQ.

But SHW doesn't have enough tenants signed up yet or it would build that tower now. It may not be able to get more office tenants to commit until the building's opening is a year away, a real estate insider told NEOtrans.

Since it's only a massing, there is no definitive size for the phase
two office tower. But this image gives a sense of what SHW
seems to want -- a tower that's roughly half the size of 
its first phase HQ tower (SHW).

"They are building expansion capacity into the new HQ, perhaps to relocate other people here to Cleveland or for another acquisition down the road," the insider said. "And they would be looking to lease that space in the short term. I've heard a few companies mentioned as possible tenants in the building. It would be the nicest, newest office building downtown, not to mention any firms that regularly do business with SHW would like to be close."

As for which companies, he declined to provide names but said they're basically any firm that is willing to pay top-of-the-market rents for a trophy-class office building. In other words, think law firms, technology, marketing, real estate and accounting firms, he said.

And, let's not forget that SHW hasn't yet included the relocation to its new HQ roughly 250 employees based in a 128,000-square-foot flex-office space on Hinckley Industrial Parkway on Cleveland's south side. SHW leased that property in 2017 for an unknown term after it acquired coatings rival Valspar for $11 billion.

Some of Valspar's employees were relocated from Minneapolis to Hinckley Industrial, according to SHW sources. Most of Valspar's corporate headquarters and research staff remain in Minneapolis. It is difficult to get a hard number on how many there are. The estimates range from 400 employees to 600 employees.

SHW is understandably very sensitive about saying anything publicly about the future location of Valspar's employees. Since it will take several years before any new SHW office space is available, SHW wouldn't want to tell its Minneapolis employees now that they'll be moving in a few years.

Until SHW builds its phase two office tower plus the low-level
development by others along West 6th and St. Clair, those
spaces will remain as surface parking lots (SHW).

That could lead to a situation where SHW would lose a lot of workers in the next several years because they have the chance to look for another job close to home. And it would be difficult for SHW to hire for those openings that will eventually relocate.

If anything, SHW has tried to reassure its Valspar employees and others in Minneapolis that they value that location.

"Minneapolis is like our second headquarters. We continue to invest in our people and product there," said former SHW spokesman Mike Conway in 2018 who also denied to NEOtrans in 2019 that SHW was even considering building a new HQ. That was months before SHW was ready to make the new HQ official.

Relocating 250 SHW flex-office workers from Hinckley Industrial Parkway and 400-600 Valspar employees from Minneapolis could fill 150,000 to 200,000 square feet of office space. That would provide a significant anchor office presence to the second tower.

Three sources reported to NEOtrans months ago that two HQ towers were planned all along, although two of the sources said neither tower would be very tall or iconic. That part turned out to be false. One of the sources said Cleveland-based architectural firm Vocon Partners was hired by SHW to do programming and spatial/massing work on a five-year contract which started last year.

In late June, SHW subcontractor Independence Excavating was
working near the northeast corner of West Superior Avenue
and West 6th, site of the phase two office tower. Next door
the 616-foot SHW HQ tower will soon join its three sky-
scraping neighbors around Public Square (KJP).

If Vocon's work was limited to the first-phase HQ tower, then it probably wouldn't need a five-year deal. If Vocon is also going to be providing services to SHW for the second tower, then it makes sense to keep them on board for more than just two to three years. It also suggests SHW wants to move forward sooner rather than later on the second tower.

So do the actions of geotechnical firms. They've drilled test bores to collect soil samples and measure the depth of bedrock at multiple locations throughout the 7-acre SHW HQ site west of Public Square. In late June, crews were doing site preparation work at the northeast corner of West Superior and West 6th -- right where the phase two tower would rise.

SHW has a lot more to gain from underselling its new HQ than from overselling it. SHW is more concerned with impressing its shareholders than those of us who admire and count the number of shiny towers in the downtown Cleveland skyline.

So whatever SHW is going to do and when is going to be determined on the potential for increasing value for its shareholder. If having more of its partner companies setting up offices next door will do that, then look for construction to start on this tower very soon.

END

Sunday, July 25, 2021

Are Bedrock's Tower City plans serious? Yes, here's why...

This rendering of what Bedrock Real Estate intends to do with the
south concourse of Tower City Center's The Avenue shopping
mall in downtown Cleveland, including a partnership with
Chain Reaction to award three entrepreneurs 18 months
of free rent at Tower City stores (Bedrock).
CLICK IMAGES TO ENLARGE THEM

Ten days ago, news broke that Bedrock Real Estate would aggressively market its Tower City Center complex so it could exchange its cobwebs and echoes for business tenants and retail customers. NEOtrans opted to not respond to this press release.

Why? Because I was skeptical about how serious Bedrock was. Understandably, shopping malls across the country were dying with some getting replaced by Amazon distribution centers. NEOtrans broke the news about several of them locally, starting with the first one at Euclid Square Mall. And all of those mall deaths occurred before the pandemic got other malls sick, too. 

Bedrock has contributed to the loss of tenants at Tower City as much as the growth of e-commerce and the decline of downtown's office workforce. But while downtown's workforce dipped, its residential population shot up and held strong through the pandemic. Residents are a more lucrative market for retail than workers who tend to make larger purchases nearer to where they live, a recent study showed. But that study also said downtown niche retail can draw customers from far away.

Furthermore, Bedrock has now owned the former Cleveland Union Terminal railroad station-turned-Tower City Center for five years and not been able to reactivate its 366,000 square feet of retail and public spaces. The opposite has happened. It has entertained previous ideas and none of them panned out, including CityBlock (NEOtrans broke the story on that one, too). So why are they are suddenly serious about redeveloping the downtown mall into, of all things, a mall? I had my doubts.

That was until this past week when two events happened.

In 1989, Tower City Center was in the midst of its conversion
from the Cleveland Union Terminal railroad station to a retail
center, office and hotel complex. But as more shopping and
lifestyle centers like Crocker Park, Legacy Village and
Pinecrest opened in the suburbs, fewer shoppers came
downtown and to Tower City (Cleveland Magazine). 

The first event was a note I received from a Bedrock source. "I’m surprised that you haven’t commented on our plans for Tower City on your blog," the source wrote.

I expressed my skepticism and asked why I shouldn't be skeptical.

"You can probably assume what you like from my having reached out to you," the source wrote. "Wish I could be more forthcoming. Keep up the good work. I know a lot of us have appreciated your blog. You seemed to know things about SW (Sherwin-Williams' headquarters site search) before we did or before they did for that matter."

The other event came two days ago from two Tower City tenants reporting to NEOtrans that they were contacted by Bedrock's local staff. The inquiries went something like this: "We'd like to know what your intentions are about remaining at Tower City Center." One was asked if it would be willing to make improvements to their retail space.

Those tenants are in a part of the mall that was unaffected by June's flood. A sprinkler above The Avenue mall at Tower City broke and flooded the mall near the Public Square entrance. Bedrock began securing city permits this week to make significant repairs to the flood damage, according to Building & Housing Department records.

An ill-fated redevelopment scheme for Tower City Center was
Bernie Moreno's CityBlock which would have turned the
mall into an incubator for technology start-ups and
other types of new businesses (Vocon).

If Bedrock is going to be courting retailers, who might they be? Let's consider the market, which involves both timing and population. And let's look at what is called "comps" in the real estate business, or comparables.

A real estate source who does a lot of work in site selections locally was contacted by NEOtrans for his input. He said Bedrock's initiative is mostly about the upcoming National Basketball Association's (NBA) All Star Game, to be held Feb. 20, 2022 in Cleveland.

To a lesser extent, the Rock & Roll Hall of Fame and Museum's induction ceremony on Oct. 30 will play a role. Both events will be held at the Rocket Mortgage Fieldhouse which is connected to Tower City by an underground walkway. Some pop-up retailers may be added by October but it will take longer for other retailers to come on board. That's why the NBA All Star Game is a bigger deal, the real estate source said.

Look for Bedrock to bring in athletic retailers like Nike, Under Armour and Moosejaw plus streetwear shops along the lines of RSVP Gallery or Bodega. Bedrock founder and Cleveland Cavaliers owner Dan Gilbert wants to put his best foot forward at the All Star Game. NBA stars start businesses. Others provide capital to them. And some are free agents, looking for a new team and a new home with cool stores to flash the cash. 

Mainstream retailers line downtown Detroit's main street of
Woodward Avenue thanks to Bedrock giving them low or
no rent for an introductory period of time (Google).

For comps, look no further than what Bedrock did to draw businesses to their properties along Woodward Avenue, Detroit's version of Euclid Avenue. They gave free or reduced rent to retailers that would draw business to benefit other nearby retailers. Finding the right mix of retailers is the key to any successful shopping area.

Along Woodward, you'll find all of the above-mentioned athletic retailers plus Bonobos, H&M, Warby Parker, lululemon, Le Labo, Shinola, Madewell, American Cycle & Fitness, UPS Store, FedEx Office, plus wine stores, day spas, drug stores, bank branches and lots of restaurants and clubs.

Those businesses alone would certainly reactivate Tower City. But what's equally intriguing is Bedrock's stated desire to work with Chain Reaction, a Cleveland-based economic development project, business bootcamp and competition that helps groom the next generation of local entrepreneurs. 

Chain Reaction is produced by Cleveland Neighborhood Progress, the Greater Cleveland Partnership’s Council of Smaller Enterprises, JumpStart and Cleveland Development Advisors. As a sponsor, Bedrock says it will provide mentorship to participants throughout the program’s duration, as well as prizes for the top three entrepreneurial finalists of their competition, combined for 18 months of brick-and-mortar tenancy at Tower City Center.

A conceptual rendering of what Tower City Center's Riverview
phase between Huron Road and the Cuyahoga River could
look like, featuring greenspaces, riverfront promenade,
plus office, hotel and residential buildings (Vocon).

And, as NEOtrans reported earlier this year, look for Bedrock to develop the Riverview phase of Tower City in the coming months and years. It has considered developing this site for some time, including for Sherwin-Williams HQ as alluded to earlier.

Now, Gilbert has one of his own locally growing corporate office end-users that will be looking for a new building soon -- Rocket Mortgage. Add to that a possible hotel and more apartments either in a new building and/or in Sherwin-Williams old HQ in the Tower City complex. They will need Tower City stores and other businesses to patronize.

Will Bedrock be able to attract the chain retailers, even by offering free rent as pop-up retailers over the coming months? Will they stay after the pop-up period expires and they have to pay rent? And how will Tower City's existing retailers who have stuck it out through some pretty dark times react to newcomers getting a free ride?

It will depend on how much new foot traffic the pop-up retailers attract to Tower City and the existing shops. There's a lot for Bedrock, Tower City and downtown retail in general to prove here. I no longer doubt Bedrock's sincerity to try something here. But there are still a lot of questions that have yet to be answered. And they will be, given time.

END

Saturday, July 24, 2021

St. Vincent expansion may unite Downtown, Campus District

St. Vincent Charity Medical Center is often overlooked in a metro
area dominated by much larger, higher-profile health care systems.
But St. Vincent has set about to change that, starting with a master-
plan to align its broadening mission to positively affect the health of
Greater Clevelanders with the facilities necessary to achieve it (CSA).
CLICK IMAGES TO ENLARGE THEM

When you take stock of St. Vincent Charity Medical Center's (SVCMC) properties and how they are used, it becomes apparent how under-utilized they are. And when considered in terms of the 156-year-old hospital's proximity to Downtown Cleveland, it's equally apparent how cut off it is.

Those and other features are among the issues to be addressed by a master-planning effort by Boston-based MASS Design Group to determine how the growing medical institution can better serve its community. Like its bigger colleagues -- Cleveland Clinic, University Hospitals and MetroHealth -- SVCMC is constrained by the surrounding city and its dependence on the car.

Nearly two-thirds of land owned or controlled by SVCMC is used for surface parking lots or as greenspace that separates buildings from sidewalks, making them less pedestrian friendly. Some of the greenspace exists for lack of another identified use.

In a written statement, SVCMC said its health campus "will encompass property owned by the Sisters of Charity at East 22nd Street and serve as a catalyst for revitalization in the surrounding area. SVCMC will be an anchor institution, partner and namesake in what will be known as the St. Vincent Charity Health Campus. Depending on what is recommended during the planning and engagement process, new services, programs and partners will be added to the existing services at SVCMC’s main campus."

While nearly all properties in and near the St. Vincent Charity
Health Campus are used, many are not used efficiently or in
ways that would improve safe and comfortable access for
populations that cannot afford to operate cars (Google).

“We work from the philosophy that our built environment should be designed to advance human dignity and promote health,” said Michael Murphy, founding principal and executive director of MASS Design Group. “The Health Campus is an opportunity for the Cleveland community to bring this philosophy to life, and create true health equity through justice and empathy.”

MASS is also serving as the lead consultant for Cleveland State University's campus masterplan. Their work on creating a vision for both campuses, as well as the next phase for the redesign of the Inner Belt/Interstate 90 corridor in 2024, is an opportunity to better link those areas. MASS representatives were in town last week to begin their work with SVCMC.

Among the goals is to not only serve the acute care needs among growing populations in nearby downtown, Ohio City, Tremont and Central, but also to improve health conditions among low-income populations in Cleveland's inner-city neighborhoods. Health care that is accessible physically as well as financially is a challenge. One in four Cleveland households has no car available -- a number that rises to one out of two households in neighborhoods with more poverty, Census figures show.

In those areas, chronic health problems such as high infant mortality rates, drug addictions and harmful effects from residential and industrial pollutants remain untreated. Addressing the health care side of those and other quality-of-life problems is a growing focus for the Sisters of Charity of St. Augustine.

Plans for redesigning the Inner Belt/Interstate 90 may help im-
prove pedestrian linkages between downtown, Cleveland State
University and the St. Vincent Charity Health Campus (ODOT).

Health care system representatives said the design process will recognize Sisters of Charity core values, serving the community with the broadest definition of health, including addressing social determinants, poverty and racial segregation, and upward mobility. Most health systems don't work on such broad issues.

"The expansion of the St. Vincent Charity main campus with partners beyond acute care can lead to a lifetime of improved community health outcomes," said Susanna H. Krey, senior vice president, Sisters of Charity Health System and president of the Sisters of Charity Foundation of Cleveland. 

And while MASS's masterplan will focus on adding facilities, services and physical linkages to SVCMC's existing properties, NEOtrans understands that it won't end there. A source close to the planning work but wasn't authorized to speak publicly said the plan may also look at underutilized properties nearby.

One of those will reportedly be the vacated, historic Cuyahoga County Juvenile Detention Center on East 22nd, between Cedar and Central avenues. There are also several underutilized parking lots nearby owned by the county. The detention center was closed in 2011 when a new facility opened on Quincy Avenue at East 93rd Street.

The interior courtyard of the former Cuyahoga County Juvenile
Detention Center on East 22nd Street (Architectural Afterlife).

The source said that the 90-year-old jail facility will likely be torn down because it cannot easily be repurposed to new uses. But the court building facing East 22nd will be retained and possibly reused.

The county has shown interest in retaining it for new uses, such as a long-term home for the county's  new Diversion Center. Currently located on East 55th Street, the diversion program treats those with substance abuse and mental problems who committed lesser offenses rather than send them to jail.

East of the old juvenile detention is one of the oldest public housing complexes still standing in Cleveland. Olde Cedar, part of the 17-acre Cedar Estates, is set to be razed and replaced with modern housing by the Cuyahoga Metropolitan Housing Authority. The first phases of replacing the 1950s-era complex were completed in 2017. Current phases include Sankofa Village and Scholar House.

In its official statement, the Sisters of Charity of St. Augustine said "Thoughtful inclusion of residents with lived experience is critical to anchoring as well as developing the vision for the initiative." Drafts of the plan could be available as early as this winter.

END

Tuesday, July 20, 2021

City OKs Sherwin-Williams HQ concept with conditions

Sherwin-Williams' new HQ tower will be Cleveland's fourth-tallest
skyscraper and be a unique shape in the city's skyline. But as mem-
bers of city planning review boards applauded the soaring tower's
 design, how the project might create or discourage interaction
with pedestrians along downtown's sidewalks was among
the concerns shared at a meeting today (SHW).
CLICK IMAGES TO ENLARGE THEM

A joint meeting of city planning committees partially approved conceptual plans for Sherwin-Williams (SHW) headquarters (HQ) today. For the portions the review panels didn't approve, they offered guidance on how to enhance the early designs to improve the pedestrian experience along downtown Cleveland's sidewalks.

The plans were jointly reviewed and approved by the Cleveland City Planning Commission, Cleveland Landmarks Commission, Downtown-Flats Design Review Committee and the Warehouse Historic District Design Review Committee. Plans included a more detailed massing whose crown was first described visually and verbally in detail here at NEOtrans earlier this month.

City officials approved SHW's location and height of buildings in its proposed vertical urban campus with these conditions and exceptions:

  • Approval excludes the northwest block of SHW land where future development by others is desired.
  • Provide a traffic study that includes pedestrian circulation.
  • Consider a pavilion height increase with public roof access.
  • Demonstrate the street-level experience of the entire site, especially the temporary lots and along Frankfort, through drawings.
  • Provide a retail strategy for the site.

Timothy Muckley, SHW's director of corporate real estate, said a new HQ is desperately needed as it has outgrown its obsolete home of 91 years at 101 W. Prospect St. He said the Landmark Office Tower suffers from low ceilings, aging mechanicals, company parking that has a 10-year wait list, and elevators that have "a mind of their own." While employees will work remotely a couple days each week, Muckley said SHW never considered relying wholly on remote employment going forward.

Timothy Muckley of Sherwin-Williams addresses a joint commit-
tee of city planning review boards to garner approval of the
coatings company's new global HQ project (TV20).

"We believe the key to innovation is to connect and collaborate," he told joint committee meeting members. "We need to be one elevator ride away from each other. While other (companies) are fighting to push people out of their headquarters, we're fighting to get them in."

He pointed out that the HQ project is desired to have these features:
  • A 616-foot-tall, roughly 36-story HQ tower that will rise at the northwest corner of Superior Avenue and West 3rd Street.
  • A site for a future office tower is reserved at the northeast corner of Superior and West 6th Street but will be held as a visitor parking lot rather than greenspace.
  • The HQ property will be secure and convenient for employees and visitors.
  • The 920-space parking garage will accommodate nearly one-third of of SHW's 3,100 HQ employees.
  • The garage was set back from St. Clair Avenue, West 3rd and West 6th to put a retail liner and/or future development around it.
  • The 2,500-square-foot retail liner along West 3rd barely exceeds the city's building code.
  • A goal of the project is to spur downtown development. SHW noted it already has, with the renovation of 55 Public Square, Rockefeller Building redevelopment, the demolition of the Rockefeller garage for a major development and the proposed Magellan development.
  • A glassy Public Square pavilion rising only two-stories and nearly 50 feet tall will pull elements out of the office tower (like a learning center, conferences, Center of Excellence, etc) and will be the cultural hub of SHW.
  • Pedestrian skybridges will connect the SHW HQ tower to its parking garage and Public Square pavilion.
The 616-foot height of SHW's HQ tower as it relates to two of its
Public Square skyscraping neighbors is shown with a future
 expansion office building of roughly 20 stories (SHW).

SHW's proposed pair of 15-foot-wide skybridges received significant pushback from planning committee members as well as at least half of the public comments received by the committee prior to the meeting. But the city cannot legally prevent them as they are permitted in the city's building code and the city recently approved two bridges to cross above Ontario Street into the JACK Cleveland Casino although only one skybridge was built.

"I understand the skybridges aren't favored but they are critical," Muckley said. "These two buildings (HQ and pavilion) need to function as one organism."

Bill Chilton, principal at Pickard Chilton, SHW's lead architect for the HQ, added that the skybridges will not pull people off of city streets. The skybridges will be open only to SHW employees. For workers going to lunch, shopping or to catch their buses and trains, they will be setting foot on downtown sidewalks when the HQ is finished in 2024. Many employees don't go outside now as the existing HQ is connected by walkways to Tower City Center.
Views from terraces on the east and west sides of the new SHW HQ
tower are shown as red lines. The maximum heights of low-level
buildings around Public Square are shown as blue lines (SHW).

Muckley said one-third of SHW employees use Greater Cleveland Regional Transit Authority (GCRTA) buses and trains. In fact, SHW officials met with GCRTA staff yesterday to improve transit access for them. SHW is using every HQ employee's home address to create a heat map of where workers live and will share it with GCRTA to seek better transit access to/from where concentrations of their employees live.

Planning committee members also questioned why the two-story, nearly 50-foot-tall Public Square pavilion was desired and/or why it was designed to be so short. They noted that Public Square is surrounded by two types of buildings -- skyscrapers and lower-level structures. The lower-level structures -- Metzenbaum U.S. Courthouse, 200 Public Square's atrium, Higbee's/JACK Casino, Renaissance Hotel and Old Stone Church -- are all in the 65- to 165-foot range of height.

Chilton said a lot of thought went into putting the pavilion and not the HQ tower on the Public Square lot, called the Jacobs Site. It's dubbed the Jacobs Site because it was previously owned by the Jacobs Group. He noted that the floor plate for the HQ, its loading docks and central utilities plant would be too big to fit on the Jacobs Site. Loading docks for the pavilion will be in the HQ tower, off Frankfort, with supplies delivered to the pavilion via the skybridge.
More views of a model showing how the new SHW HQ tower,
its parking garage and Public Square pavilion would relate
to its downtown Cleveland surroundings (SHW).

"We view the pavilion as the front door to Sherwin-Williams," Chilton said. "As for putting the (HQ) tower on the Jacobs Site, it creates tension with Terminal Tower. Pulling it back (to West 3rd) gives it that relief. When looking at it (the HQ tower) from different views around the city, it retains views and allows terminal Tower to breath visually."

The pavilion will have at its southwest corner a Barista store filled with Sherwin-Williams-branded merchandise, such as clothing, coffee mugs and other promotional items. But those reportedly will be for employees. Right now, SHW hasn't decided whether to make the pavilion open to the public, said Matt Heisey, principal at Vocon Partners, SHW's interior architect.

Warehouse District Executive Director Tom Yablonsky suggested opening up the pavilion to public access, enlarging it and putting a café on its rooftop. He added that a taller pavilion would also make the skybridge across West 3rd appear less prominent.
Major components of the first phase of SHW's HQ (SHW).

Furthermore, city planning officials expressed concern about pedestrian flows between the Warehouse District, Public Square and Euclid Avenue where transportation, restaurants and stores are located for downtown residents and businesses. SHW will direct its traffic engineering consultant Nelson Nygaard to also evaluate pedestrian traffic flows through the HQ site.

Frankfort Avenue between West 3rd and West 6th is being vacated as a city street and will become SHW property. SHW will close it off to through traffic for vehicles but leave it open to pedestrians. There will be bollards or some other vehicular barrier on Frankfort just west of West 3rd. Employee vehicles entering the parking garage will stack up on Frankfort in the mornings. Delivery trucks to SHW are also more numerous in the mornings. After work, employee vehicles will exit onto West 3rd.

However, Muckley said Frankfort will be landscaped and, at the city's urging, be the subject of a retail study that could possibly result in raising the garage's ground level from 11 feet to 20 feet to accommodate more ground-floor retail uses.
A screenshot from today's meeting showing the SHW HQ model
that includes the future phase expansion building (TV20).

The site for future expansion of the SHW HQ also received some attention -- both by SHW's Muckley and by city planning representatives. Muckley said SHW needs to have room for expansion as the company has grown rapidly in the last few decades.

"We've made this mistake with manufacturing plants of not planning for the future," he said. "We want this to be our headquarters site for a long time. It's important to be able to have that for growth."

Even though a significant structure of roughly 20 stories is shown in basic massings of the HQ campus, SHW officials declined to discuss publicly when it might need to build that second office building. Muckley did say that no new parking facilities are anticipated for that future building. The proposed parking garage will not be designed to construct additional levels on top of it. He said the future expansion site would temporarily remain as a parking lot.

"I've been on this (city planning) committee for a long time," responded Thomas Zarfoss, a retired landscape architect. "Whenever I hear the term 'temporary' it gets my attention. To make cities walkable, you can't be walking along parking lots."

Public Square pavilion and HQ tower podium connections (SHW).

Before the HQ project was officially acknowledged by SHW, NEOtrans reported information from sources close to the project that the HQ+R&D project would measure as much as 1.8 million square feet and ultimately accommodate up to 6,000 employees. About 1,000 of those workers will be based in the new 500,000-square-foot research center in Brecksville.

HQ design team sources say the first-phase, 1-million-square-foot office tower will have enough space for 3,500 employees although 3,100 office workers will be located there at the outset. If the 6,000-employee, 1.8-million-square-foot goal for the HQ+R&D is still the target, another 1,500 workers have yet to find their way into the HQ campus. Another 300,000 square feet office space may be coming.

SHW has yet to include in its HQ plans any efforts to relocate more than 250 workers from its 151,830-square-foot swing/office space at 4780 Hinckley Industrial Parkway in Cleveland. Or, for that matter, there are roughly 1,000 workers in Minneapolis in facilities previously owned by Valspar until SHW acquired the rival company in 2017.

A phase two office building measuring 300,000+ square feet for roughly 1,500 or more employees appears to be on SHW's to-do list. But it's not likely to make any of that public until after it takes care of its first priority -- its new, 21st-century global HQ and research facilities. 

END

Friday, July 16, 2021

Westinghouse site may see $85 million reno with hotel, apartments, shops

Looming large over the West Shoreway is the Westinghouse plant
which has stood there for nearly 140 years and sat vacant for the
last five. It is proposed to be redeveloped by a local investor
who reportedly has deep pockets (Google).
CLICK IMAGES TO ENLARGE THEM  

When an abandoned industrial property has a great location and great views, eventually the right investor with the right program at the right time is going to find it and redevelop it no matter how difficult that site is.

The latest property to fit that bill is the abandoned Westinghouse factory along Cleveland's West Shoreway, located at 1200 W. 58th St. at the north end of the Gordon Square neighborhood. It has several factors going for it this time, despite at least one prior attempt that came up empty.

One of those factors is the investor himself. Michael Trebilcock, founder and chairman of Cleveland-based data protection company MCPc Inc, has enjoyed great success in business. He also founded a real estate firm called Trebilco Properties to invest his wealth in improving Greater Cleveland.

According to sources close to the project but who were not authorized to speak about it publicly, Trebilcock is seeking to redevelop the Westinghouse property with a boutique hotel, apartments, shops and parking. The site features 303,000 square feet of connected structures including an eight-story building that looms over the Shoreway.

Looking north on West 58th Street from the Gordon Square
neighborhood, the Westinghouse plant "steps up" toward
the lake. Some of the lower-level buildings in the
factory complex were demolished (KJP).

The estimated cost of the redevelopment is $85 million, they said. The Krill Co. of Cleveland is being engaged as the project's general contractor and Los Angeles-based AECOM was chosen as the architect. AECOM has an office in Cleveland.

In a brief phone interview, Trebilcock confirmed his interest in the Westinghouse property which is currently owned by the Kole family of Westlake, doing business as Paramount-Breakwater Properties, LLC. It is listed for sale at $6 million.

"We're really at the tail end of getting through the acquisition," he said. "We're moving in on closing the purchase in about four to six weeks."

As for sharing more details, such as the hotelier's name, number of apartments, or types of retailers/restaurants in the proposed programming for the redeveloped Westinghouse property, Trebilcock was mum.

"I'd rather not say anything at this point," he said. "But it's exciting."

An overhead view of the Westinghouse plant in August 2020,
showing the extensive development around it. Compare it to
the photo from five years earlier, shown below (Google).

The sources also were unwilling to share many details about the programming, but they acknowledged that the boutique hotel would be the dominant use for the eight-story building with residential as a secondary use.

Westinghouse's tower is 122 feet tall and measures 112,000 square feet. The lower-level parts of the complex are proposed to have unidentified shops and parking. They measure 191,000 square feet and date to 1882. Those structures are 1-3 stores tall, some with high, truss-supported ceilings and unconventional floor plans.

In the decades that Westinghouse owned the plant, the low-level structures were full of heavy machinery such as drop forges, foundries and presses as well as polishing, annealing and anodizing processes, according to a former employee. That means finding resources to not only redevelop the site but potentially to clean it up.

Another timing factor working in the favor of a redeveloped Westinghouse property is the availability of significant new public funding resources. They include the Transformational Mixed Use Development (TMUD) tax credit program as well as $350 million in new state funding for environmental clean up of abandoned industrial properties.

A birdseye view from 2015 of the Westinghouse plant before the
north end of the Gordon Square neighborhood was substantially
redeveloped primarily with new residential uses (Google).

The TMUD program will have $100 million in tax credits for large real estate development projects statewide in each of the next four years. Of that, $80 million will go to developments in and near Ohio's six largest cities, benefitting projects with price tags of at least $50 million, standing 15 or more stories or measuring at least 350,000 square feet.

For Westinghouse to qualify, it would have to add nearly 50,000 square feet of space. If it didn't add space, the project could go the route of tapping historic tax credits to overcome the project's high costs. When asked if he would pursue a TMUD credit, Trebilcock was non-committal.

"There's lots of options for financing," he said. "We're running the gamut at this point."

The timing may also be improving for attracting a boutique hotel to Cleveland, which doesn't have any luxury brands in or near downtown. That omission was duly noted in efforts that began last year to redevelop the Flats West Bank with mixed uses including an upscale boutique hotel. The market research showed Cleveland could support one but the pandemic kept hoteliers from committing at that time.

Ward 15 Councilman Jenny Spencer and Detroit-Shoreway Community Development Organization Director Adam Stalder did not respond to e-mails seeking comment prior to publication of this article.

END

Thursday, July 15, 2021

45 Erieview aims to be Cleveland's first post-pandemic remote-work tower

The curving floorplates of 45 Erieview offer sweeping
views of Lake Erie for residents, but interior parts of
the building cannot be used for apartments because
the city's building code requires residential uses
to have windows. So the interior spaces will
be for work spaces and a wide range of
amenities for tenants (KJP).
CLICK IMAGES TO ENLARGE THEM

When you pore over Bluelofts Inc.'s proposed floor plans for the planned remake of 45 Erieview Plaza, several thoughts come to mind. The first one is that this appears to be the first development in Cleveland to take into account new remote-working lifestyles sought in a post-pandemic world.

That becomes apparent when you realize that the proposed development would have a stunning offering of amenities that could turn this building into a city-within-a-city. Such as.... 

Indoor putting green plus two golf simulators? Check. Movie theater and a community gaming room? Check. Rock-climbing wall, half-court basketball and pickleball court? Check. Co-working lounge and coffee/cocktail lounge? Check. Steam and massage rooms? Check. Barbershop and salon? Peloton video room? Pet spa and grooming room? You get the idea.

It's almost like being on the Axiom in the movie Wall-E -- minus the tubby people in the floaty chairs and the acceleration to hyperspace.

Ground floor plan detail for 45 Erieview  --
By the way, after you click on the image, right-click
on the enlarged image and select "open image in new
tab" where you can enlarge it further (Dimit).

But is this building, located at East 9th Street and Lakeside Avenue, cartoonish science fiction, too? That's a lot of costly amenities to put in a building in downtown Cleveland where rising rents are still below those of larger coastal cities.

Bluelofts, combined with investor Kenny Wolfe, each hailing from Dallas, acquired the building and nearby 348-space parking garage for $21 million, according to sources who spoke off the record. There are also 32 parking spaces under the building, located at the southeast corner of Lakeside Avenue and East 9th Street.

Selling the property was New York-based private equity firm Somera Road, county records show. The buyers intend to start $50 million worth of renovations and improvements by November, with optimistic completion date of late-2022 or early 2023, the sources said.

Option 1 for a second-floor plan for 45 Erieview (Dimit).

But what makes this project more intriguing is that it is more responsive to a post-pandemic world than possibly any other existing building or pending development in downtown Cleveland. And Bluelofts has experience with live-work conversion projects, mostly in southern cities.

Their plan for 45 Erieview mixes apartments and work spaces for residential tenants in the conversion of a relatively modern, 16-story office tower. This building, constructed in 1983 as the headquarters for the Ohio Bell Telephone Co., may well be the perfect place to accommodate post-pandemic remote-work lifestyles.

The reason is the 492,864-square-foot building has sprawling office floors that measure about 37,000 square feet. Most office floorplates are under 30,000 square-feet; residential towers are even less. The floor sizes perplexed other potential buyers who passed on signing purchase agreements because they couldn't imagine how to use the big floors.

Option 2 for a second-floor plan for 45 Erieview (Dimit).

But the curving, outer walls of the building's glassy north face are an attraction as they offer terrific views of Lake Erie. So that's where 200 market-rate apartments will be located. In the interior of the building is where the largely window-less work spaces for residents will be. The city's building code requires residential uses to have windows; it doesn't require them for work spaces.

The presence of so many amenities also will be useful to residents who would live in what is still predominantly an office district. There aren't as many residential amenities here as there are further south along East 9th near Euclid Avenue.

However, James Kassouf, owner of the nearby Erieview Tower and Galleria, is proposing to add residential to the 40-story tower and supportive amenities to the Galleria. But those proposals were made several years ago when Kassouf bought the property. Little visible activity has happened since.

END

Seeds & Sprouts XVIII -- Hingetown bags grocer, Innovation Square to rise, Franklin West spaces out

This is the Eighteenth edition of Seeds & Sprouts - Early intelligence on Cleveland-area real estate projects. Because these projects are very early in their process of development or just a long-range plan, a lot can and probably will change their final shape, use and outcome.

This ground-floor site plan for Church+State in Ohio City's Hingetown
section shows which retail spots are leased and which ones are still
available. About half the ground-floor spaces are leased -- a feat
considering the hardships endured by many retailers during
the pandemic (Cleveland Building Department).
CLICK IMAGES TO ENLARGE THEM

Hingetown's Church+State bags small grocery store

Nature's Oasis will add its third store in the Greater Cleveland area and its first in the City of Cleveland when it opens at the end of the year in the new Church+State development. The site is in the Hingetown section at the north end of the Ohio City neighborhood.

Graham Veysey, a principal in the Church+State project, confirmed the healthy, all-natural foods grocer will take about 3,500 square feet in Church, the shorter of the two buildings. Church is six stories tall while State tops out at 11. The development is named after Church Avenue and West 29th Street that was called State Street before north-side Cleveland streets were numbered in 1906. The store will open up on to Church Avenue.

Nature's Oasis first store is in downtown Lakewood with its second at the new Van Aken District in Shaker Heights. Their markets have hundreds of local products including bread and other baked goods, dairy products, produce, tea, coffee and more.

The grocer will join other new tenants at Church+State including Green Opal Salon and Great Lakes Health & Wellness; their leases were first reported by NEOtrans. They were joined by fitness center Corus45 which recently occupied a storefront facing Detroit Avenue.

The first phase of Fairfax Renaissance's Innovation Square is
getting ready to start construction. It is a big step forward for
the redevelopment of East 105th Street and the Opportunity
Corridor south of University Circle (City Architecture).

Innovation Square to build around holdout property

Look for construction work to start in the coming weeks to prepare the site for the first phase of Fairfax Renaissance Development Corp.'s Innovation Square development. That became a realistic possibility this week when plans for an 82-unit, mixed-income apartment building at 2260 E. 105th St. were submitted to the Cleveland's Building Department. The apartment building will be called Square 105.

Site improvements include removal of six areas of contaminated soils that will be placed in a pit, compacted and covered with 2 inches of clean fill material. General contractor McCormack Baron Salazar will also oversee removal of all pavements, structures, basements, poles, utilities and trees. Additionally, a new street will be added -- an extension of Hudson Avenue to the west side of East 105th.

However, Fairfax is going to have to work around a small property it has not yet been able to acquire for Square 105. The 0.074-acre parcel is owned by Clemark Property Associates Ltd. which also owns other east-side parcels. It acquired the property in 2016 after it was forfeited to the state, following the conviction of its prior owner Mark Makupson.

Site plan for Square 105, the first phase of the Innovation Square
that will also include new single-family homes and more multi-
family buildings. This phase is working around an East 103rd
Street property that has yet to be acquired (City Architecture).

He was sentenced to 13 years in prison for his reported leadership role in an interstate drug trafficking ring. Makupson's sentence was shortened because he testified against fellow drug dealers and three East Cleveland police officers. But he had to forfeit various assets including 2245 E. 103rd St.

According to Ohio Secretary of State records, Clemark was created by Makupson but now lists to Marquetta Makupson of Bowling Green. No relationship is known. Tax mailings for the property go to Tatiana Franklin of Wickliffe who also operates CRF Medical Staffing Agency, according to Cuyahoga County records and Google searches.

Estimated construction cost of Square 105 is about $10 million, according to the Ohio Housing Finance Agency which provided $8 million in tax credit equity to the project. The funding will provide for the site improvements, a 76-space parking lot (proposed for 93 spaces if 2245 E. 103rd can acquired) and the 79,500-square-foot apartment building.

This is an artist's rendering of the Franklin West apartments, 4815
Franklin Blvd., in Cleveland's Ohio City neighborhood (Bowen).

Ohio City apartment project drives parking solution

While construction continues on the 24-unit Franklin West apartments, 4815 Franklin Blvd. in Cleveland's Ohio City, the developer has made a change to the project to accommodate the 25 required parking spaces for it.

Developer My Place Group LLC, owned by Chad Kertesz, previously received a parking variance for 20 parking spaces on site with the five remaining required spaces in the Iglesia Del Salvador Church, 4801 Franklin, parking lot on the east side of West 48th Street.

According to a filing with the building department, when the site layout was engineered, it was determined that only 15 spaces could fit on the site with the townhouse-style apartments.

My Place Group notified the city it had revised its lease agreement with the church to increase the number of leased parking spaces to 10. The total allotted number of spaces for the development is 15 on site and 10 in the church parking lot to achieve the required number of parking spaces.

END