Sherwin-Williams seeks builders for HQ + R&D project
That process suggests that SHW is on a schedule that could have them start construction on a new HQ and R&D project by 2022. And some aspects of the process point toward downtown Cleveland as the site for most, if not all of this massive project.
According to a source, a Request For Qualifications (RFQ) was sent to a small number of construction management firms in Greater Cleveland for the construction of a new headquarters and research center for Sherwin-Williams. The source didn't identify which firms received the RFQ, but it was reportedly sent by SHW's real estate broker CBRE.
An RFQ is intended to reduce the number of bidders on a project to only those with the expertise to qualify for the project. So then why issue it to so few firms to start with?
A logical assumption is that an RFQ was issued because SHW needs a highly specialized construction manager. Furthermore, considering that so few firms received the RFQ, it suggests that SHW apparently needs a level of expertise that few local construction management firms have.
What expertise? It isn't known for certain, but the temptation is point to firms that know how to build supertall skyscrapers, like those that reach up to 900 feet tall and require caissons excavated 200 feet down to Cleveland's bedrock.
Either number is large enough to mean that the project includes both the HQ and the R&D. It doesn't mean they'll be in the same building or even on the same property. But it does mean they could be part of the same construction bid.
Another source says that if an office campus of shorter buildings for an HQ+R&D near downtown or in the suburbs was under serious consideration, then the RFQ probably would have been sent to many more local construction management firms. It apparently wasn't.
That all leads to the next big question: where would the HQ+R&D be built? The RFQ apparently didn't identify the project's location except that it would be in the Greater Cleveland area and it would total 1.8 million square feet. The construction firm, when selected, will then presumably learn where the project will be built.
Vocon Partners, LLC is reportedly designing conceptual alternatives, including for different locations downtown. It isn't publicly known where those sites are. One site that is likely to be strongly considered is the site where SHW planned in 2014-15 to consolidate its scattered offices -- the Jacobs lot on Public Square.
Councilman Kerry McCormack, whose Ward 3 includes downtown Cleveland, didn't sound terribly worried about SHW leaving downtown Cleveland for the suburbs.
"We're in good communication with Sherwin-Williams," he said. "We'll do whatever it takes to keep them. But companies that want to attract talent are looking at moving into cities, not leave them."
While there are a lot of moving parts at work here, and based on the timeline of past projects, it is possible that facility conceptual designs, programming, infrastructure and other components could be ready for delivery to a city's planning commission in as soon as a year from now.
SHW representatives would likely request approval of conceptual plans, then refine them into more detailed schematic designs. Approval of the conceptual plans will first require releasing them publicly. That's when the public will probably get its first official notice of the project. The 6,000 SHW employees involved, as well as civic-minded Clevelanders, will have to wait until then.
Thankfully, at least SHW is no longer officially denying that there may be an HQ+R&D project on the horizon. They've confirmed they are analyzing their HQ space needs, but are peddling the theme that they do such analyses regularly. That's pretty unlikely considering the last time SHW moved into a new HQ building was 1930.
several facilities beyond its aging, 900,000-square-foot Landmark Office Tower HQ where employees have complained of uncomfortable climate controls, lack of open floor layouts and even roaches. SHW's apparently random leasing of additional offices since 2014 doesn't scream "coherent plan."
Offices are located among three non-contiguous floors totaling 51,810 square feet in the Skylight Office Tower, a remodeled 151,830-square-foot flex space at 4780 Hinckley Industrial Parkway in Cleveland, as well as in 30,000 square feet of the Automotive Finishes Corp. facility, 4440 Warrensville Center Rd. in Warrensville Heights.
That doesn't include the 140,293-square-foot Breen Technology Center in downtown Cleveland and the former Valspar Applied Science & Technology Center in downtown Minneapolis. That complex includes several renovated historic structures and totals more than 170,000 square feet.
If combined into a new facility that offered more elbow room plus space for future expansion, it could mean an R&D center of 330,000 square feet or more. Parking for thousands of employees and visitors would add roughly 350 square feet per parking space in a multi-level structure. It isn't publicly known if the 1.8 million square feet figure for the HQ+R&D includes parking.
What is known is that SHW's debt burden from the 2016-17 Valspar acquisition is shrinking at an increasing rate. Six months ago, SHW had been on a glidepath to get its long-term debt-to-equity (D/E) ratio down to 2:1 by December 2019.
But it's already five months ahead of that pace. Last year, SHW looked like it would reduce its long-term debt to $8.12 billion by June 30, 2019. Instead, it fell to $7.2 billion. Shareholder equity is only slightly below where it was destined to be on June 30. It was on target to be about $3.77 billion. Instead it was at $3.75 billion at the mid-year point.
SHW debt-to-equity ratio on June 30 was already below 2:1 -- at 1.92:1, thanks to strong cash flow from the Valspar acquisition.
According to second-hand sources, SHW officials have said that the company wouldn't consider building a new HQ until its debt was down to reasonable levels. "Reasonable" may well mean the coatings industry average of a 1:1 D/E ratio.
Last year, it appeared SHW was on a glidepath to hit that 1:1 D/E ratio at the end of 2022. But if cash flow continues to be strong and shareholder equity continues to rise steadily, SHW should get its D/E down to 1:1 in a little more than two years from now.
That's roughly when the planning, programming, design and procurement should allow for construction of the HQ+R&D facilities to begin. Fingers crossed.
END
Tuesday, August 20, 2019
NuCLEus development stalls -- again?
The nuCLEus development, as seen from Huron Road at East 4th Street and next to the expanded Rocket Mortgage Field House (Stark). CLICK IMAGES TO ENLARGE |
One source says the project is on hold. The other says the project is dead. The reason why the project apparently has stalled isn't completely clear.
However, according to one rumor, it appears that there may be differences of opinion between the city and Stark as to how helpful one has been to the other. Some of that was suggested by recent events.
On Aug. 15, and at the request of Ward 3 Councilman Kerry McCormack, the Downtown/Flats Design Review Committee tabled a request by B&B Wrecking Inc. to demolish a condemned, four-story building at 310 Prospect Ave.
B&B Wrecking is a Stark contractor. Stark owns the property and the structure, called the Herold Building, through an affiliate Herold Building LLC. The structure was built in 1900 and measures 15,720 square feet, according to Cuyahoga County records.
Stark and its nuCLEus partner, J-Dek Investments Ltd., own the neighboring 16-space parking lot property through a partnership Gateway Huron, LLC. Both properties would reportedly serve as a single staging area during the construction of nuCLEus.
The Herold Building is within a National Historic District and is a designated National Historical Landmark. The previous owner, Los-Angeles-based L&R Group of Companies, tried to demolish the Herold Building for a new but smaller building. It was rebuffed by the city. Stark pledged to refurbish the building when it bought the property in 2014. Since then, however, the building has only decayed further.
Outlined in green, the Herold Building at 310 Prospect Ave. is proposed for demolition, apparently to help create a staging area for the construction of nuCLEus (Stark). |
"The city is looking for a detailed plan," McCormack said in an Aug. 19 interview. "I have not been briefed on what the plan is. In general, if you're going to demolish a building, the last thing we need is a surface parking lot. I don't know if that's what they propose. We just want to see a plan."
In an interview several weeks ago, following an article reporting that demolition for nuCLEus was scheduled to start in mid-August, Stark Enterprises' Chief Operating Officer Ezra Stark declined comment about the possible demolitions that could also include a 418-space parking deck at 611 Huron and an historic building at 618 Prospect featuring Mr. Albert's Men's World clothier.
However, Stark said the reason why he declined comment on the demolitions was due to a delicate "political" matter. He offered no further details.
"I don't even know how to answer that question anymore -- I hear it a lot," said the councilman whose ward includes downtown. "My understanding is it's still alive."
Stark first announced nuCLEus five years ago, long before it or J-Dek had most of the financing in place to develop the project. That was when nuCLEus was planned to be a 54-story skyscraper.
The current plan for NuCLEus is that it would feature two 24-story towers atop a pedestal of retail and parking between Prospect Avenue and Huron Road at East 4th Street. One tower would feature 400,000 square feet of offices; the other 250 residential units.
While it was reported in late June that nuCLEus now has most of its financing in place, others in Cleveland real estate circles dispute this. Some believe that nuCLEus is far from finalizing its capital stack.
In yet another of the rumors surrounding nuCLEus, Stark apparently is redirecting capital resources -- including Opportunity Zone program funds which have time constraints on their use -- to projects in other cities including Pittsburgh.
"I think we have a solid economic development package" that's been offered by the City of Cleveland, Cuyahoga County and the State of Ohio to aid nuCLEus, McCormack volunteered.
Saturday, August 17, 2019
Midtown property sale designed to spur new development
This a conceptual masterplan of the Penn Square area of Cleveland's Midtown, with the Greater Cleveland Regional Transit Authority's property outlined in blue (Pennrose). CLICK IMAGES TO ENLARGE |
The sale is the latest example of intensifying interest in rejuvenating this once-vibrant neighborhood that's been relegated to pass-through status for more than 40 years.
GCRTA has a tentative deal with Civic Property Development LLC to sell seven parcels totaling 2.38 acres at 5508-5810 Euclid Ave. for $550,000. The Cleveland Foundation will also contribute $50,000 to aid in the planning of a transit oriented development (TOD) project or projects on the site, in partnership with GCRTA.
The foundation created Civic Property Development, filing incorporation documents with the state on May 15, to support this development site and possibly others in the future. The Cleveland Foundation has for years supported programs and projects to boost Cleveland neighborhoods, especially Midtown.
The Cleveland Foundation's conceptual plan for its new head- quarters (at right) and a new Center for Innovation. This view looks north up East 66th Street from Euclid Avenue (CF). |
The Cleveland Foundation proposes a three-story, 50,500-square-foot headquarters building on the northeast corner of of Euclid and East 66th. On the northwest corner, the foundation proposes a future Center For Innovation measuring 100,000 square feet.
While the immediate vicinity of Midtown and Hough has seen more than $400 million worth of development in the last decade, 40 percent of area residents and 66 percent of children live in poverty, according to the city.
It isn't known yet what would be planned for the GCRTA property, but TOD typically features dense, mixed-use residential and commercial development with less emphasis on parking and more attention to walkability and, thus, transit access. The site is next to the East 59th Street station stop on GCRTA's HealthLine bus rapid transit.
Looking east on Euclid Avenue in September 2018 from below the Norfolk Southern railroad overpass. The vacant, GCRTA- owned property is visible at right (Google). |
The Euclid-East 55th area was called Penn Square for more than 100 years because the main Cleveland railroad passenger station for the Pennsylvania Railroad was located here. Travelers could board and alight 24 daily passenger trains to/from places as far west as St. Louis and as far east as New York City.
Two busy streetcar lines also crossed here, carrying as many riders as all of Northeast Ohio's transit agencies combined do today. The neighborhood once had the density and activity of a 24-hour, satellite downtown, with large apartment and commercial buildings, shops, cafes and theaters.
It was sold in 1977 to the DiGeronimo family, doing business as Ace Realty, and leased it to several tenants. The properties continued to decline. DiGeronimo, in turn, sold the land in 2002 to Lassi Enterprises, LLC, a subsidiary of MidTown Cleveland Inc., a community development corporation.
Midtown transferred it to GCRTA in 2005 so that it could demolish the handful of decaying buildings remaining on the property. Here, GCRTA established a construction staging site for its $200 million Euclid Corridor (later called HealthLine) that was completed in 2008. The properties have remained vacant ever since. GCRTA put the land up for sale in 2017.
END
Condos to rise at Avenue District this fall
** UPDATED SEPT. 4 **
The working title for the project is The Avenue Condos-Phase II, because it would be located at 1325 East 12th St. It is in the area where Zaremba Group planned and began building a multiple-structure, multiple-phase development along and between East 12th and 15th streets, as well as St. Clair and Superior avenues on the northeast side of downtown Cleveland.
Like Zaremba before it, Geis plans a shorter building just north of the first phase. The reason why this site was chosen is because the existing foundations for phase II that were built in 2008. However, they cannot support a larger structure.
Zaremba in the late 2000s built a 10-story Avenue District condominium building, which since has offered units for rent, and 20 for-sale townhomes. Another 16 for-rent townhomes were built along East 15th, called the Milton Townhomes. All are now Geis-managed properties.
More for-sale townhomes are being built in the Avenue District by Knez Homes. They are selling quickly despite listing at prices near $500,000, or $250 per square foot. The 12-unit first phase sold out as construction continues, with a second phase of up to 24 homes approved by City Planning Commission. Knez is easily exceeding its 50-percent presale goals for each phase.
Rumors about the new condo building have circulated for a while, but became official when the project appeared on the city's Design-Review docket. Planning documents were submitted to the city in July and meetings were held with top city officials to move the project forward. GLSD, Geis' in-house architect, designed the project.
Geis representatives were not prepared to comment publicly at this time.
The tower is the favored address of Cleveland professional sports stars, business executives, medical specialists in Cleveland’s globally regarded health care field, and others seeking the best in luxury downtown living.
There are rumors that Geis may be interested in building a new condo tower on East 9th Street at Bolivar Road.
Downtown Investment Group LLC, a Geis Companies affiliate, bought the former New York Spaghetti House and razed it for future development. Although there is not yet a timeline for this project, the city in 2015 gave Geis permission to use the property for a parking lot for up to five years.
Geis representatives aren't commenting on that project either.
END
The working title for the project is The Avenue Condos-Phase II, because it would be located at 1325 East 12th St. It is in the area where Zaremba Group planned and began building a multiple-structure, multiple-phase development along and between East 12th and 15th streets, as well as St. Clair and Superior avenues on the northeast side of downtown Cleveland.
Like Zaremba before it, Geis plans a shorter building just north of the first phase. The reason why this site was chosen is because the existing foundations for phase II that were built in 2008. However, they cannot support a larger structure.
Site of the Avenue District Condos-Phase II as seen from the construction site of the phase I building in February 2008. As one can see, foundations for Phase II already exist (KJP). |
More for-sale townhomes are being built in the Avenue District by Knez Homes. They are selling quickly despite listing at prices near $500,000, or $250 per square foot. The 12-unit first phase sold out as construction continues, with a second phase of up to 24 homes approved by City Planning Commission. Knez is easily exceeding its 50-percent presale goals for each phase.
Rumors about the new condo building have circulated for a while, but became official when the project appeared on the city's Design-Review docket. Planning documents were submitted to the city in July and meetings were held with top city officials to move the project forward. GLSD, Geis' in-house architect, designed the project.
Geis representatives were not prepared to comment publicly at this time.
Site plan for Geis's Phase II of the Avenue District. North is at the top of this image (GLSD). |
The tower is the favored address of Cleveland professional sports stars, business executives, medical specialists in Cleveland’s globally regarded health care field, and others seeking the best in luxury downtown living.
Downtown Investment Group LLC, a Geis Companies affiliate, bought the former New York Spaghetti House and razed it for future development. Although there is not yet a timeline for this project, the city in 2015 gave Geis permission to use the property for a parking lot for up to five years.
Geis representatives aren't commenting on that project either.
END
Monday, August 12, 2019
It's official: Westinghouse redevelopment fizzles
NEOtrans broke the news about the renovation in January, and it again broke news on Aug. 9 that the project to convert the 303,000-square-foot vacant industrial complex into residential, parking and perhaps other uses might not happen.
However, no official reason was available at the time. There were rumors that the project, located in Cleveland's Detroit-Shoreway neighborhood, had floorplans that were too complicated or that there was on-site pollution left over from prior users that had to be cleaned up.
"It is the case that we are not moving forward," said Josh Rosen, a principal at Sustainable Community Associates, at UrbanOhio in response to a posting of the NEOtrans article on its public forum.
"It (is) not for a specific reason or anything speculated (in the Aug. 9 NEOtrans article) -- it is just as simple as we hard time matching up our sources and uses," Rosen added. "It is an awesome set of buildings and we hope a catalytic project emerges."
Part of the Westinghouse plant was demolished for a parking lot for the newly built Edison apartments. But most of the rest of the Westinghouse plant remains intact (LoopNet). |
The tower has great views of Lake Erie, Edgewater Park and downtown Cleveland. The surrounding neighborhood is rapidly developing with new housing including the Edison apartments, Battery Park, plus many smaller townhouse developments.
But the source said a major question was what to do with the low-level structures, measuring 191,000 square feet and dating to 1882. Those structures are 1-3 stores tall, some with high, truss-supported ceilings and unconventional floor plans.
A mere 50,000 square feet might be needed for indoor parking to support about 100 apartments that could fit in the tower, leaving roughly 140,000 square feet among the low-level structures without an identified use.
Converting the remainder of the low-level structures to residential or offices could also require environmental clean up. During the decades that Westinghouse owned the plant, those structures were full of heavy machinery such as drop forges, foundries and presses as well as polishing, annealing and anodizing processes, according to a former employee.
One thing is for certain, Westinghouse would have been the largest redevelopment project, by far, undertaken by Sustainable Community Associates. Crain's Cleveland Business reported in February that Midwest Development Partners was considering joining forces in the project in an apparent attempt to increase the endeavor's access to capital sources.
The property remains available for sale, listed at $6 million.
END
Friday, August 9, 2019
Westinghouse, Blanket Mills conversions face adversity
But we don't see the arduous environmental analyses, the endless paperwork, the frequent meetings and, of course, the stumbles. If we did, many of us would probably have no desire to become a real estate developer -- if not for the joy of seeing the finished product. And if he or she is lucky, a developer will deliver a finished product more than half of the times he or she tries.
So the situations involving the residential conversions of the Westinghouse Electric and Manufacturing Co., 1200 W. 58th St., as well as the Northern Ohio Blanket Mills, 3160 W. 33rd St., offer some similarities. But they are at different stages of stumbling, er, development.
Conversion of the 303,000-square-foot, mostly vacant Westinghouse plant next to the West Shoreway is apparently going to take longer and cost more than some originally had expected. And it may not be purchased and renovated at all by Sustainable Community Associates as its principals Josh Rosen, Naomi Sabel and Ben Ezinga likely had hoped.
Jeff Ramsey, executive director at Detroit Shoreway Community Development Organization, said he also heard the rumor but hasn't be able to confirm it with Rosen et al. That may suggest that Sustainable Community Associates isn't yet ready to declare defeat.
News of this project was broken by NEOtrans last January.
A major issue, according to the source, is that the developer hasn't identified a use for the lower-level buildings in the Westinghouse plant. By contrast, reusing the eight-story, 122-foot-tall, 112,000-square-foot, 1915-built tower as residential is a no-brainer.
But what to do with the low-level structures, measuring 191,000 square feet part and dating to 1882? Those are 1-3 stores tall, some with high, truss-supported ceilings and unconventional floor plans. A mere 50,000 square feet might be needed for indoor parking to support about 100 apartments that could fit in the tower.
Part of the Westinghouse plant was demolished for a parking lot for the newly built Edison apartments. But most of the rest of the Westinghouse plant remains intact (LoopNet). |
One thing is for certain, Westinghouse would be the largest redevelopment project, by far, undertaken by Sustainable Community Associates. Crain's Cleveland Business reported in February that Midwest Development Partners joined forces on the project, likely to increase the endeavor's access to capital.
By contrast, redevelopment of the Northern Ohio Blanket Mills in the Clark-Metro neighborhood appears to be moving forward after years of hopes and disappointments. Redevelopment of the 2.2-acre property, owned by Derek Ng, has been proposed for 10 years.
city approvals process at the City Planning Commission. If successful, Ng's persistence will have paid off. That persistence may also inspire backers of the Westinghouse project.
The Northern Ohio Blanket Mills was listed in 2014 on the National Register of Historic Places because the factory was the largest manufacturer of woolen horse blankets and carriage robes in the world.
It was founded by Herman Beckman Sr. in 1880 on West 33rd, then-called Pleasant Street. The original structure was destroyed by a fire in February 1888 but rebuilt just a year later. The factory was expanded in the 20th century as the company diversified its woolen product lines.
A portion of the factory was renovated more than a decade ago as the Lin Omni Center, 3167 Fulton Rd. In 1912, the Lin Omni was the last building built as part of the Northern Ohio Blanket Mill. St. Rocco Church is immediately south of the old factory. Ng also owns the 650,000-square-foot, vacant Richman Brothers factory, 1600 E. 55th St.
END
Thursday, August 8, 2019
City Club tower nearly ready to rise on Euclid Ave.
A new 22-story apartment tower on Euclid Avenue in downtown Cleveland is due to be announced soon by City Club Apartments (CCA). CLICK IMAGES TO ENLARGE THEM |
The new apartment tower, proposed to be located on a surface parking lot where the Hippodrome Building and Theater stood until 1981, will fill the last major "missing tooth" in the Euclid Avenue streetscape. It just so happens that the site chosen by the City Club chain is next to the historic City Club Building, 850 Euclid Ave.
City Club has apartment properties and development projects in Chicago, Detroit, Ann Arbor, Minneapolis, Kansas City, Louisville, Cincinnati, Pittsburgh and elsewhere. The chain owned an under-performing, 400-unit apartment building in St. Louis but sold it last year to New York-based Emerald Equity Group for $48 million.
“We appreciate and respect the city of St. Louis and its leadership, but have made the decision to focus the growth of our portfolio on other Midwest and East Coast markets,” said Jonathan Holtzman, chief executive officer of City Club Apartments in RE Journals. “We have a responsibility to our investors, lenders and partners to perform at the highest level and we are reallocating our financial and human capital to several accelerating markets including Cleveland.”
A cursory review of new 22-story residential buildings throughout the USA shows that the number of apartments in those towers range from 170-350 units, but most are in the 250-300 apartments range. Two Cleveland apartment towers of comparable size -- the nearly completed Beacon and the planned nuCLEus apartment building -- offer deceptively small residential components.
The Beacon's residential component is only 19 stories tall but is built atop an existing, nine-story parking garage. Its floor plates are about 12,350 square feet. Thus, it offers only 187 apartments. Similarly, nuCLEus' 24-story apartment tower has 250 units in just 16 floors of residential, built atop a planned eight-story pedestal of retail and parking.
City Club's tower could be similar. It will reportedly feature ground-floor commercial spaces and parking above, topped by residential. The 70-space parking lot on which the City Club Apartments would be built measures about 25,000 square feet.
A 22-story, 457,575-square-foot, $70 million apartment high-rise proposed in the St. Louis suburb of Clayton shows a comparable scale for City Club's tower (Flaherty & Collins). |
About 17 stories might be left for residential in the new City Club tower. The Beacon tower averages 1,255 square feet per apartment. If City Club is comparable, at 250 units, its residential component could be about 313,703 square feet or 18,500 square feet per floor. At 300 units, its residential component could about 376,444 square feet or 22,144 square feet per floor.
The City Club tower development appears to be a joint venture with property owner David Goldberg, as no property has yet changed hands. Not having to buy land will help reduce City Club's development costs, as will the shared parking opportunity in the existing deck. Thus it possible that the project, measuring 440,000 to 500,000 square feet, could be delivered for less than $100 million.