The large mixed-use development combining residential, retail and offices in two connected, uniquely timber-framed buildings at Lorain Avenue and West 25th Street was in danger of being axed by an impasse between the city and Chicago-based developer Harbor Bay Real Estate Advisors.
On one side, Harbor Bay sought a source of non-conventional financing that included an unusually long (30 years) and expansive (affecting not just residential but commercial uses, too) property tax abatement without civic and public input.
And while the school district and Cleveland Metroparks were willing to consider a shorter abatement term, the City of Cleveland refused to concede its abatement powers to a state entity -- in this case the Ohio Air Quality Development Authority (OAQDA).
But the impasse was addressed at a Sept. 11 meeting between city officials and the developer. The project could go forward with city incentives rather than state help, although the development probably won't be in the same form as before, according to Harbor Bay Project Director Dan Whalen.
"We likely will have to revamp" the project, he said. "But we are moving quickly."
With West 25th Street in the foreground and West Side Market's tower at far left, Market Plaza will be a significant addition to Ohio City's Market District and its urban vibrancy (HPA). |
"The project is 70 percent bid and we can hold those prices for only a limited time," he said.
Harbor Bay has invested nearly $10 million in the project so far, including buying a retail strip for which it has city permits in hand to demolish. City officials acknowledged the renewed positive dialogue and a shared willingness to move the project forward.
"Yes, there are productive conversations with Harbor Bay," said Ward 3 Councilman Kerry McCormack confirmed. "The (city's) normal economic development tools are on the table."
Those typically include a 15-year, 100 percent tax abatement on new-construction residential, with a tax-increment financing arrangement so the city can share the increased income taxes with the school district during the abatement period.
OAQDA's Aug. 13 board meeting. But last-minute letters of of opposition from the city, school district and metroparks nixed the financing and abatement.
OAQDA was approached because Market Square's timber framing would reduce emissions by 40 percent mostly from reduced heating and cooling, but also from avoiding the manufacture of steel and concrete. The most recent plan was for a 10-story office building and seven-story apartment building connected by a pedestal of ground-floor retail.
While Whalen wasn't prepared to say how the project would be changed, he said the timber framing for the buildings would remain.
"Timber will still be the focal point," he said.
Whalen also noted that all of Market Square's office and retail tenants will be new to Greater Cleveland, bringing more than 1,000 jobs and nearly $11.8 million per year in new sales and incomes taxes to the city and county.
END
So, the new version of the Market Square will be still smaller than your 2nd depiction of it here?
ReplyDeletePossibly. There will be less financial resources available to the project but how much remains to be seen.